Friday, July 31, 2009

Thermal Bag Sealer

1. PURPOSE

It is established to provide a proper procedure for Poly bag sealing in different departments to protect the product from dust.

2. SCOPE

It is applicable in different packaging department.

3. RESPONSIBILITY

Maintenance officer (Mechanical / Electrical)
Maintenance Supervisor (Mechanical / Electrical)

4. PROCEDURE

The Thermal Bag Sealer with instrument is handled in the following way.


5. MAINTENANCE

MONITORING OF MACHINE MAINTENANCE:

Time to time check each and every part of Thermal Bag Sealer according to the maintenance schedule
Check the following parts carefully.
vElectric Transformer
vMicro Switch
vSealer Element
vSealer Ribbon
This activity is then documented in the form Machinery & Equipment Maintenance Log
Check the Thermal Bag Sealer condition time to time to find any kind of problem during operation.
All the monitoring record is filed and kept by the Maintenance Supervisor.
EMERGENCY / BREAKDOWN MONITORING:

Maintenance Manager receives Maintenance Work Order duly signed by the section incharge of the concerned machinery or equipment.
Maintenance Work Order is assigned a number according to the receiving in the Maintenance Reference Register.
Maintenance Manager assigns the maintenance work to the concerned personal
After the completion of work the section incharge signs the completion of Work Order.
All the record is filed and kept by the Maintenance Supervisor.


PRECAUTIONS:

Take extreme care while using electrical equipments.
Immediately switch to “OFF” if find any kind of noise, spark etc.

No comments: