1. PURPOSE
It is established to provide a proper procedure for the maintenance being done in the facility.
2. SCOPE
It is applicable in the maintenance department.
3. RESPONSIBILITY
Maintenance officer (Mechanical / Electrical)
Maintenance Supervisor (Mechanical / Electrical)
Maintenance Manager
4. PROCEDURE
EMERGENCY / BREAKDOWN MAINTENANCE:
Maintenance Manager receives Maintenance Work Order duly signed by the section incharge of the concerned machinery or equipment.
Maintenance Work Order is assigned a number according to the receiving in the Maintenance Reference Register.
Maintenance Manager assigns the maintenance work to the concerned personal
After the completion of work the section incharge signs the completion of Work Order.
All the record is filed and kept by the Maintenance Supervisor.
PLANNED PREVENTIVE MAINTENANCE:
The maintenance manager along with production manager plans the preventive maintenance schedules.
The planned preventive maintenance schedule is forward to each department.
Any modification in collaboration with section incharge is discussed and finalized.
The intimation for maintenance schedule work is sent 3 to 4 days before the planned preventive maintenance date.
After the approval of section incharge maintenance manager assigns the duty to the concerned personnel.
At the end of maintenance all the activity is documented properly.
MONITORING OF MACHINE MAINTENANCE:
The maintenance staff time to time checks the machinery. Any deviation or problem is immediately forward to the maintenance manager for further activity.
Any problem arose communicated to the maintenance staff by production staff is forward to the maintenance manager for further activity.
Subscribe to: