Thursday, July 30, 2009

S.S Pumps

1. PURPOSE

It is established to provide a proper procedure for transmission of water/liquid in different production departments.

2. SCOPE

It is applicable in the different production departments.
3. RESPONSIBILITY

Maintenance officer (Mechanical / Electrical)
Maintenance Supervisor (Mechanical / Electrical)

4. PROCEDURE

The S.S. Pumps with instrument is handled in the following way.

5. MAINTENANCE

MONITORING OF MACHINE MAINTENANCE:

Time to time check each and every part of S.S. Pump according to the maintenance schedule.
Check the following parts carefully.
 Electric motor
 Electric Starter
 Mechanical Seal
 Pump Impeller
This activity is then documented in the form Machinery & Equipment Maintenance Log
Check the S.S Pump condition time to time to find any kind of problem during operation.
All the monitoring record is filed and kept by the Maintenance Supervisor.


EMERGENCY / BREAKDOWN MONITORING:

Maintenance Manager receives Maintenance Work Order duly signed by the section incharge of the concerned machinery or equipment.
Maintenance Work Order is assigned a number according to the receiving in the Maintenance Reference Register.
Maintenance Manager assigns the maintenance work to the concerned personal
After the completion of work the section incharge signs the completion of Work Order.
All the record is filed and kept by the Maintenance Supervisor.

PRECAUTIONS:

Do not operate the pump when the valve is in closed position.
Switch to “OFF” the pump if find any kind of abnormality during operations.